I-35E Utility Relocation Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Water and Wastewater Relocation

Project Description:

The scope of work for the project includes abandoning or removing and replacing existing water and wastewater lines along the I-35E Frontage roads and under I-35E in preparation for TxDOT's expansion of the roadway. A portion of this work will also include water and wastewater lines along the 1171 crossing (Main Street) and Business 121 near Texas Street.

Project Cost and Funding Sources:

  • The project will be initially funded through the City's utility capital projects fund and is reimbursable through TxDOT funding.
  • Phase One was awarded to SAI Construction in June 2022 for $3.2 million.
  • Phase Two was awarded to Canary Construction Inc., in July 2023 for $9.6 million.  Construction will start August 2023. 

Estimated Completion:

  • Phase One completed July 2023.
  • Phase Two, Corporate Blvd. to Huffines Blvd., is projected to be completed September 2024. A map of the area is below.
Location Map

Questions and City Contacts:

Call 972.219.3510 during non-working hours if an urgent need arises on weekends or overnight.

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Windows Media Player Download Windows Media Player Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer